Guides
Roofing takeoff guides
Cover width, pitch, flashings and waste. Check the product sheet and the NZMRM Code of Practice before you order.
- Sheet count from effective cover width
NZ longrun sheet count is ceiling of ridge-direction width including verges, divided by cover. Dimond corrugate 762 mm not 851 mm. Hip roofs need waste on top.
- Dimond corrugate vs Metalcraft corrugate
Dimond corrugate 762 mm cover; Metalcraft 760 mm. Both 8° min cladding pitch. Never count from 851 mm overall. Metalcraft 9° past 30 m sheets.
- Longrun drainage run checks
This takeoff warns when slope length passes the CoP check-run. It does not replace the NZMRM maximum-run calculator or a HIRDS rainfall figure.
- Extra High wind zone on a NZ roof order
Extra High is Category B flashing cover at all pitches (200 mm ridge, two barge upstands). Sheet count often unchanged. Very High under 10° is also Category B here.
- Five NZ ribbed profiles and where they fit
Match corrugate 8°, Six Rib 4°, Hi Five/T-Rib 3°, and tray 3°/60 m to the job. Count from cover width, not overall sheet width.
- Ridge, barge, hip and valley flashing takeoff
Measure each flashing line on the slope. Extra High is Category B cover at every pitch (200 mm ridge). Do not bury trims in sheet waste.
- Hi Five on a low-pitch NZ roof
Dimond Hi Five is a 27 mm five-rib trapezoidal with 3° min cladding pitch and 765 mm cover. Confirm the coil and South Island supply before you count sheets.
- How many roofing sheets for a NZ roof?
Divide ridge-direction width by cover and round up per plane. Then slope length, CoP pitch, flashings and hip waste. Not area ÷ a made-up sheet size.
- NZ longrun roofing material takeoff
Count NZ longrun sheets from cover width, add flashings and waste, then check CoP pitch and run length before you order.
- Low-pitch longrun — Hi Five, Six Rib and tray
Below 8° corrugate is the wrong product. Six Rib 4°/20 m; Hi Five 3°/40 m (765 mm cover, South Island listed); tray needs the named pan.
- From NZ roof measurements to a merchant order
Turn plan length, span, pitch and a named NZ profile into a merchant sheet-and-flashing list. Cover width, slope length, CoP pitch and shape-based waste.
- Merchant-order takeoff checklist
Screenshot the takeoff plus written assumptions: planes, cover, lengths, CoP pitch, run, EH flashings, waste. Not a quote.
- Metal tile roofing NZ takeoff
Count metal tile sheets from effective cover width, check pitch and NZS 4217, then add flashings and waste before you order.
- Checking a roof against minimum cladding pitch
Compare as-laid pitch to CoP 7.1.1A and the named sheet. Corrugate 8°/15 m, Six Rib 4°/20 m, Hi Five 3°/40 m, tray 3°/60 m. Not design pitch.
- Multi-section NZ roof takeoff
Give every plane its own pitch, cover, run and flashings. Adding footprints at one pitch is how a 4° lean-to disappears.
- NZ longrun roof profiles
Pick an NZ longrun profile from cover width, min cladding pitch and run-length check, not from a catalogue photo. Corrugate, trapezoidal and tray numbers from CoP and manufacturer sheets.
- Roof pitch questions before you order
Before ordering, write as-laid cladding pitch, named profile, manufacturer extras, and wind zone. 8° corrugate is not 6°. Design pitch on the truss is not enough.
- Secret-fix tray minimum pitch in NZ
CoP generic secret-fix ~30 mm is 3° / 60 m. Named trays differ. This library uses 300 mm cover as a placeholder — override the pan.
- Choosing a secret-fix tray for a NZ roof
Secret-fix is clips under the pan, not pierce-fixed ribs. Library 300 mm / 3° / 60 m is a placeholder. Count from named cover. Pitch FAQ: /guides/secret-fix-tray-pitch.
- Longrun sheet length from slope
Sheet length is slope including eaves, not plan span. This takeoff rounds up 50 mm. Check CoP run after 15–60 m depending on profile.
- Tray cover width before you order
Secret-fix sheet count uses named pan cover, not overall width and not this library’s 300 mm placeholder. Real NZ pans are often 265–500 mm.
- Roofing waste on hips, valleys and complex NZ roofs
Gable longrun waste is mostly per-plane round-up. Hips start ~12% of sloped area; each valley adds 3%. Flashings are separate lineal metres.