Choosing a secret-fix tray for a NZ roof

Secret-fix (tray / trough) is a different family from pierce-fixed corrugate and trapezoidal. Clips sit under the rib. There are still fasteners — they are not through every weathering face. Do not specify clips or seams from a photo. Pitch questions: secret-fix tray minimum pitch.

Cover is the order width

This library’s tray is 300 mm cover / 325 mm overall / 3° / check after 60 m, CoP secret-fix ~30 mm. Real pans are often 265–500 mm. Heritage Tray (Dimond example) is about 450 / 465 mm / 3°.

9.2 m ÷ 0.450 m = 20.44 → 21 sheets. Using 465 mm overall → 20 and a shortage. Override cover on the takeoff when you know the pan.

When not to lock tray

Then stop and get the manufacturer or an LBP. The calculator will still run the CoP 3°/60 m row if you leave the placeholder — that is a warning aid, not an approval.

Takeoff sequence

  1. Write manufacturer, pan name, cover, clip type, max length.
  2. Split planes (multi-section).
  3. Count from cover; length from slope including eaves.
  4. Tray flashings (grab / verge / ridge / wall), not generic barge from corrugate (flashing checklist).
  5. Extra High still changes junction cover.

NZMRM CoP profile classification and the named PTS remain the authority.